Wind farm league table

Which of Britain's wind farms ran hardest lately, ranked by load factor: each farm's average output as a share of its capacity, over the last 7 or 30 days.

Last 7 days: 5 November to 11 November 2026, 333 half hours recorded. 9 wind farms not yet running in full and 2 sending no power are listed last, unranked.

#Wind farmOwnerCapacityAverageLoad factor
1Pen y Cymoeddonshore · 72 of 228 MWVattenfall228 MW72 MW32%
2Craigonshore · 1 of 5 MW–5 MW1 MW22%
3Rampionoffshore · 87 of 400 MWRWE400 MW87 MW22%
4Keith Hillonshore · 1 of 5 MW–5 MW1 MW20%
5East Anglia Oneoffshore · 143 of 725 MWScottishPower725 MW143 MW20%
6Robin Riggoffshore · 34 of 174 MWRWE174 MW34 MW19%
7Galloperoffshore · 68 of 353 MWRWE353 MW68 MW19%
8Couronshore · 4 of 21 MWFern Trading21 MW4 MW19%
9London Arrayoffshore · 120 of 630 MWRWE630 MW120 MW19%
10Windy Rigonshore · 8 of 43 MWGreencoat UK Wind43 MW8 MW19%
11Hornsea 1offshore · 225 of 1,200 MWØrsted1,200 MW225 MW19%
12Westermost Roughoffshore · 38 of 205 MWØrsted205 MW38 MW19%
13Hornsea 2offshore · 238 of 1,320 MWØrsted1,320 MW238 MW18%
14West of Duddon Sandsoffshore · 71 of 398 MWØrsted398 MW71 MW18%
15Solwaybankonshore · 5 of 30 MWTRIG30 MW5 MW17%
16Beinn an Tuirc IIIonshore · 9 of 52 MWScottishPower52 MW9 MW17%
17Walneyoffshore · 59 of 366 MWØrsted366 MW59 MW16%
18Humber Gatewayoffshore · 35 of 219 MWRWE219 MW35 MW16%
19Walney Extensionoffshore · 106 of 675 MWØrsted675 MW106 MW16%
20Neart na Gaoitheoffshore · 70 of 448 MWEDF448 MW70 MW16%
21Vikingonshore · 76 of 488 MWSSE488 MW76 MW16%
22Crossdykesonshore · 7 of 48 MWOctopus Energy Generation48 MW7 MW16%
23Lincsoffshore · 42 of 270 MWØrsted270 MW42 MW15%
24Race Bankoffshore · 87 of 574 MWØrsted574 MW87 MW15%
25Hywind Scotlandoffshore · 5 of 30 MWEquinor30 MW5 MW15%
26Moray Eastoffshore · 132 of 900 MWOcean Winds900 MW132 MW15%
27Gwynt y Môroffshore · 86 of 592 MWRWE592 MW86 MW14%
28Greater Gabbardoffshore · 77 of 539 MWSSE539 MW77 MW14%
29Sheringham Shoaloffshore · 45 of 316 MWEquinor316 MW45 MW14%
30Blackcraigonshore · 7 of 56 MWTemporis Capital56 MW7 MW13%
31Kincardineoffshore · 7 of 50 MWACS Group50 MW7 MW13%
32Dudgeonoffshore · 53 of 402 MWEquinor402 MW53 MW13%
33Thanetoffshore · 39 of 300 MWVattenfall300 MW39 MW13%
34Kype Muir Extensiononshore · 9 of 67 MWGreencoat UK Wind67 MW9 MW13%
35Seagreenoffshore · 135 of 1,075 MWSSE1,075 MW135 MW13%
36Cumberheadonshore · 6 of 52 MWOctopus Renewables Infrastructure Trust52 MW6 MW12%
37Twenty Shillingonshore · 5 of 38 MWGreencoat UK Wind38 MW5 MW12%
38Douglas West Extensiononshore · 8 of 66 MWCapital Dynamics66 MW8 MW12%
39Gunfleet Sandsoffshore · 20 of 172 MWØrsted172 MW20 MW12%
40Freasdailonshore · 3 of 22 MWTRIG22 MW3 MW12%
41Aftononshore · 6 of 50 MWRed Rock Power50 MW6 MW12%
42Crystal Rig IVonshore · 5 of 48 MWFred. Olsen Renewables48 MW5 MW11%
43Whiteside Hillonshore · 3 of 28 MWVantage RE28 MW3 MW11%
44Blary Hillonshore · 4 of 35 MWTRIG35 MW4 MW11%
45Aikengall IIonshore · 7 of 64 MWCommunity Windpower64 MW7 MW11%
46Minscaonshore · 4 of 38 MWNadara38 MW4 MW11%
47Moray Westoffshore · 94 of 860 MWOcean Winds860 MW94 MW11%
48Greengairs Eastonshore · 4 of 38 MWMuirhall Energy38 MW4 MW11%
49Tullymurdochonshore · 2 of 14 MWTemporis Capital14 MW2 MW11%
50Beatriceoffshore · 62 of 588 MWSSE588 MW62 MW11%
51Ewe Hill IIonshore · 4 of 38 MWScottishPower38 MW4 MW11%
52Ormondeoffshore · 16 of 151 MWVattenfall151 MW16 MW10%
53Fallago Rigonshore · 14 of 144 MWFederated Hermes144 MW14 MW10%
54Glenchamberonshore · 3 of 27 MWFern Trading27 MW3 MW10%
55An Suidheonshore · 2 of 19 MWRWE19 MW2 MW10%
56A'Chruachonshore · 4 of 43 MWNadara43 MW4 MW10%
57Halsaryonshore · 3 of 30 MWScottishPower30 MW3 MW10%
58Sanquharonshore · 3 of 32 MWCommunity Windpower32 MW3 MW10%
59Beinn an Tuirc 2onshore · 4 of 44 MWScottishPower44 MW4 MW9%
60Baillieonshore · 5 of 53 MWStatkraft53 MW5 MW9%
61Kilgalliochonshore · 21 of 228 MWScottishPower228 MW21 MW9%
62Burbo Bank Extensionoffshore · 23 of 258 MWØrsted258 MW23 MW9%
63Burn of Whilkonshore · 2 of 23 MWEneco23 MW2 MW9%
64Triton Knolloffshore · 73 of 824 MWRWE824 MW73 MW9%
65Bad a' Cheòonshore · 2 of 27 MWRWE27 MW2 MW9%
66Limekilnonshore · 9 of 106 MWBoralex106 MW9 MW9%
67Pogbieonshore · 1 of 10 MWHermia Community Energy10 MW1 MW9%
68Carraig Ghealonshore · 4 of 46 MWRailpen46 MW4 MW9%
69Crystal Rig IIIonshore · 1 of 14 MWFred. Olsen Renewables14 MW1 MW9%
70Dorenellonshore · 15 of 177 MWEDF177 MW15 MW9%
71Camster IIonshore · 3 of 36 MWRWE36 MW3 MW9%
72Braes of Douneonshore · 6 of 74 MWGreencoat UK Wind74 MW6 MW8%
73Strathy Northonshore · 6 of 70 MWSSE70 MW6 MW8%
74Hagshaw Hillonshore · 7 of 81 MWScottishPower81 MW7 MW8%
75Barrowoffshore · 7 of 90 MWØrsted90 MW7 MW8%
76Kennoxheadonshore · 5 of 60 MWPerigus Energy60 MW5 MW8%
77Goole Fieldsonshore · 3 of 33 MWRWE33 MW3 MW8%
78Glen Apponshore · 2 of 22 MWScottishPower22 MW2 MW8%
79Aberdeen Bayoffshore · 8 of 99 MWVattenfall99 MW8 MW8%
80Aikengall IIaonshore · 7 of 82 MWCommunity Windpower82 MW7 MW8%
81Camsteronshore · 4 of 50 MWRWE50 MW4 MW8%
82Tom nan Clachonshore · 3 of 40 MWGreencoat UK Wind40 MW3 MW8%
83Gordonbushonshore · 6 of 72 MWSSE72 MW6 MW8%
84Harestanesonshore · 11 of 142 MWScottishPower142 MW11 MW8%
85Dalswintononshore · 2 of 30 MWNadara30 MW2 MW7%
86Clydeonshore · 38 of 550 MWSSE550 MW38 MW7%
87Minnygaponshore · 2 of 25 MWCK Infrastructure25 MW2 MW7%
88Rosehallonshore · 2 of 25 MWRWE25 MW2 MW7%
89Corriemoillieonshore · 3 of 48 MWEDF48 MW3 MW7%
90Gordonbush Extensiononshore · 3 of 38 MWSSE38 MW3 MW7%
91Cumberhead Westonshore · 9 of 126 MWScottishPower126 MW9 MW7%
92Clachan Flatsonshore · 1 of 15 MWScottishPower15 MW1 MW7%
93Burbo Bankoffshore · 6 of 90 MWØrsted90 MW6 MW6%
94Coire na Cloicheonshore · 2 of 31 MW–31 MW2 MW6%
95Pines Burnonshore · 2 of 36 MWCapital Dynamics36 MW2 MW6%
96South Kyleonshore · 14 of 240 MWGreencoat UK Wind240 MW14 MW6%
97Gordonstownonshore · 1 of 13 MWNadara13 MW1 MW6%
98Whiteleeonshore · 18 of 309 MWScottishPower309 MW18 MW6%
99Beinn Tharsuinnonshore · 2 of 30 MWScottishPower30 MW2 MW6%
100Toddleburnonshore · 2 of 28 MWSSE28 MW2 MW6%
101Harburnheadonshore · 3 of 52 MWGresham House52 MW3 MW6%
102Dersallochonshore · 4 of 71 MWScottishPower71 MW4 MW6%
103Assel Valleyonshore · 2 of 26 MWNadara26 MW2 MW6%
104Whitelee Extensiononshore · 11 of 206 MWScottishPower206 MW11 MW6%
105Andershawonshore · 2 of 35 MWGreencoat UK Wind35 MW2 MW6%
106Clashindarrochonshore · 2 of 39 MWVattenfall39 MW2 MW5%
107Strathroryonshore · 2 of 37 MWCapital Dynamics37 MW2 MW5%
108North Kyleonshore · 11 of 212 MWBrockwell Energy212 MW11 MW5%
109Hill of Towieonshore · 3 of 48 MWTRIG48 MW3 MW5%
110Berry Burnonshore · 3 of 63 MWStatkraft63 MW3 MW5%
111Hare Hill Extensiononshore · 2 of 30 MWScottishPower30 MW2 MW5%
112Stronelairgonshore · 11 of 228 MWSSE228 MW11 MW5%
113Mid Hillonshore · 4 of 76 MWFred. Olsen Renewables76 MW4 MW5%
114Rothes IIonshore · 2 of 42 MWFred. Olsen Renewables42 MW2 MW5%
115Kilbrauronshore · 3 of 69 MWNadara69 MW3 MW5%
116Enoch Hillonshore · 3 of 70 MWRWE70 MW3 MW5%
117Lochluichartonshore · 3 of 69 MWEneco69 MW3 MW5%
118Benbrackonshore · 3 of 67 MWRed Rock Power67 MW3 MW5%
119Black Law Extensiononshore · 3 of 69 MWScottishPower69 MW3 MW4%
120Tralorgonshore · 1 of 19 MWRailpen19 MW1 MW4%
121Griffinonshore · 9 of 206 MWSSE206 MW9 MW4%
122Broken Crossonshore · 2 of 43 MWERG43 MW2 MW4%
123Creag Riabhachonshore · 4 of 93 MWERG93 MW4 MW4%
124Dalquhandyonshore · 2 of 43 MWGreencoat UK Wind43 MW2 MW4%
125Dunlaw Extensiononshore · 1 of 30 MWScottishPower30 MW1 MW4%
126Hill of Glaschyleonshore · 1 of 28 MWMuirden Energy28 MW1 MW4%
127Sandy Knoweonshore · 3 of 87 MWERG87 MW3 MW4%
128Paul's Hillonshore · 3 of 70 MWFred. Olsen Renewables70 MW3 MW4%
129Auchrobertonshore · 1 of 36 MWNadara36 MW1 MW4%
130Kype Muironshore · 3 of 89 MWOnPath Energy89 MW3 MW4%
131Mark Hillonshore · 2 of 53 MWScottishPower53 MW2 MW4%
132Airiesonshore · 1 of 38 MWNTR38 MW1 MW4%
133Black Lawonshore · 4 of 118 MWScottishPower118 MW4 MW4%
134Dunmaglassonshore · 4 of 100 MWSSE100 MW4 MW4%
135Corriegarthonshore · 3 of 69 MWGreencoat UK Wind69 MW3 MW4%
136Galawhistleonshore · 2 of 55 MWNadara55 MW2 MW4%
137Tullo Extensiononshore · 1 of 25 MWEneco25 MW1 MW4%
138Arecleochonshore · 4 of 114 MWScottishPower114 MW4 MW3%
139Glen Kyllachyonshore · 2 of 52 MWGreencoat UK Wind52 MW2 MW3%
140Crystal Rig IIonshore · 5 of 151 MWFred. Olsen Renewables151 MW5 MW3%
141Rothesonshore · 2 of 55 MWFred. Olsen Renewables55 MW2 MW3%
142Causeymireonshore · 2 of 48 MWNadara48 MW2 MW3%
143Edinbaneonshore · 1 of 41 MWVattenfall41 MW1 MW3%
144Glens of Foudlandonshore · 1 of 27 MWBlackRock27 MW1 MW3%
145Middle Muironshore · 1 of 51 MWOnPath Energy51 MW1 MW3%
146Bhlaraidhonshore · 3 of 108 MWSSE108 MW3 MW3%
147Farronshore · 2 of 92 MWNadara92 MW2 MW3%
148Douglas Westonshore · 1 of 45 MWGreencoat UK Wind45 MW1 MW3%
149Tulloonshore · 0 of 17 MWEneco17 MW0 MW3%
150Moyonshore · 2 of 60 MWEneco60 MW2 MW2%
151Beinneunonshore · 2 of 109 MWFern Trading109 MW2 MW2%
152Millenniumonshore · 1 of 65 MWNadara65 MW1 MW1%
–Brockloch Rig 2onshore · – of 62 MWFred. Olsen Renewables62 MW–Sending no power
–Dogger Bank Aoffshore · – of 1,200 MWSSE1,200 MW–Not yet running in full
–Dogger Bank Boffshore · – of 1,199 MWSSE1,199 MW–Not yet running in full
–East Anglia Threeoffshore · – of 680 MWScottishPower680 MW–Not yet running in full
–Hadyard Hillonshore · – of 117 MWSSE117 MW–Sending no power
–Hornsea 3offshore · – of 330 MWØrsted330 MW–Not yet running in full
–Inch Capeoffshore · – of 1,080 MWRed Rock Power and ESB1,080 MW–Not yet running in full
–Kilgallioch Extensiononshore · – of 50 MWScottishPower50 MW–Not yet running in full
–Pencloeonshore · – of 81 MWInvenergy81 MW–Not yet running in full
–Priestgillonshore · – of 44 MWMuirhall Energy44 MW–Not yet running in full
–Sofiaoffshore · – of 1,400 MWRWE1,400 MW–Not yet running in full

Over the last 7 days, Pen y Cymoedd (32%), Craig (22%) and Rampion (22%) ran hardest.

What load factor means

A wind farm's load factor is its average output divided by its capacity. A 400 MW farm that averaged 160 MW over the week has a load factor of 40%. No wind farm runs flat out for long: the wind drops, turbines are taken out for servicing, and the farm's own limits on the grid connection can cap it. Offshore farms usually run at a higher load factor than onshore ones, because the wind at sea is stronger and steadier. Over a single week the figure swings a lot with the weather, which is why the 30-day table is the fairer comparison.

Where the figures come from

Every half hour GridMonkey records each farm's physical notification from Elexon: the output it has told the grid it will run at, the same figure the wind farm pages show live. It is the farm's own plan for the half hour, not metered output, so it doesn't show the grid asking a farm to turn down at short notice; on very windy days, when that happens most, a farm's real output can be lower. The average is over the half hours recorded in the period. The tables fill in from the day GridMonkey started counting each farm's daily output: the 7-day table within a week, the 30-day table within a month. A farm added to the list later is averaged over the half hours since it was added, and ranked once GridMonkey has recorded it for half the period. Capacity is each farm's registered generating capacity, from Elexon's register.

The list covers the wind farms that have their own balancing mechanism units, 163 of them. Hundreds of smaller farms trade through suppliers' combined units and are not listed one by one. For how clean Britain's electricity has been each month, see the monthly grid reports.

Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register.

Every wind farm in Britain, live

GridMonkey shows every wind farm's output right now as one big pie, and rolls the farms up by owner. Free, no sign-up.