Loading the live figure from Elexon…
Output over the last 7 days
Camster II since 2025: every month and year
Elexon's metered record for Camster II's unit starts on 17 December 2025, and runs to 24 October 2026. In that time it has generated 45.4 GWh. Its best day was 5 April 2026, when it generated 705 MWh, 29 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 45.4 GWh | 18% |
| 2025from 17 Dec | 0 MWh | 0% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, E_CMSTW-2, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Camster II
Camster II is an onshore wind farm in Highland, Scotland, with 36 MW of registered generating capacity across one balancing mechanism unit. It is the 127th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by RWE. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Camster II as operational since April 2026, with 10 turbines of 3.6 MW, up to 127 m tall to the blade tip.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 36 MW |
| Turbines | 10 turbines of 3.6 MW |
| Height to blade tip | 127 m |
| Operational since | April 2026 |
| Location | Highland, Scotland |
| Grid region | North Scotland |
| Owner group | RWE (operator or majority owner; joint ventures simplified) |
| Operator in REPD | E.ON UK |
| Elexon lead party | Edgware Energy Limited |
| BM unit | E_CMSTW-2 36 MW |
| Size | 127th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Camster II, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Camster II Wind Farm: Live Output and History Since 2025. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/camster-ii/ (Accessed: [date]).
Other RWE wind farms
- Sofia offshore, 1,400 MW
- Triton Knoll offshore, 824 MW
- London Array offshore, 630 MW
- Gwynt y Môr offshore, 592 MW
- Rampion offshore, 400 MW
- Galloper offshore, 353 MW
- Humber Gateway offshore, 219 MW
- Robin Rigg offshore, 174 MW
- Enoch Hill onshore, 70 MW
- Camster onshore, 50 MW
More wind farms in North Scotland
- Mid Hill onshore, 76 MW
- Braes of Doune onshore, 74 MW
- Paul's Hill onshore, 70 MW
- Berry Burn onshore, 63 MW
- Moy onshore, 60 MW
- Rothes onshore, 55 MW
- Baillie onshore, 53 MW
- Beinn an Tuirc III onshore, 52 MW
- Kincardine offshore, 50 MW
- Causeymire onshore, 48 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since December 2025 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.