Output over the last 7 days
Kennoxhead since 2021: every month and year
Elexon's metered record for Kennoxhead's unit starts on 2 November 2021, and runs to 24 October 2026. In that time it has generated 569 GWh. Its busiest whole year was 2025, at a load factor of 26%. Its best day was 18 February 2026, when it generated 1,390 MWh, 58 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 123 GWh | 29% |
| 2025 | 139 GWh | 26% |
| 2024 | 121 GWh | 23% |
| 2023 | 120 GWh | 23% |
| 2022 | 66.1 GWh | 13% |
| 2021from 2 Nov | 0 MWh | 0% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_KENNW-1, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Kennoxhead
Kennoxhead is an onshore wind farm in Strathclyde, Scotland, with 60 MW of registered generating capacity across one balancing mechanism unit. It is the 86th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Perigus Energy. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Kennoxhead as under construction in the July 2026 edition (it may already be generating some of its output), with 13 turbines of 4.8 MW, up to 180 m tall to the blade tip.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 60 MW |
| Turbines | 13 turbines of 4.8 MW |
| Height to blade tip | 180 m |
| Status | Under construction (REPD, July 2026) |
| Location | Strathclyde, Scotland |
| Owner group | Perigus Energy (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Ørsted Onshore |
| Elexon lead party | Kennoxhead Wind Farm Limited |
| BM unit | T_KENNW-1 60 MW |
| Size | 86th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Kennoxhead, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Kennoxhead Wind Farm: Live Output and History Since 2021. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/kennoxhead/ (Accessed: [date]).
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since November 2021 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.