Loading the live figure from Elexon…
Output over the last 7 days
Blackcraig since 2019: every month and year
Elexon's metered record for Blackcraig's unit starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 1.2 TWh. Its busiest whole year was 2020, at a load factor of 35%. Its best day was 14 November 2025, when it generated 1,266 MWh, 53 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 139 GWh | 35% |
| 2025 | 149 GWh | 30% |
| 2024 | 131 GWh | 27% |
| 2023 | 140 GWh | 28% |
| 2022 | 163 GWh | 33% |
| 2021 | 141 GWh | 29% |
| 2020 | 173 GWh | 35% |
| 2019from 1 Feb | 148 GWh | 33% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_BLKWW-1, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Blackcraig
Blackcraig is an onshore wind farm in Dumfries and Galloway, Scotland, with 56 MW of registered generating capacity across one balancing mechanism unit. It is the 88th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Temporis Capital. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Blackcraig as operational since March 2018, with 23 turbines of 2.3 MW.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 56 MW |
| Turbines | 23 turbines of 2.3 MW |
| Operational since | March 2018 |
| Location | Dumfries and Galloway, Scotland |
| Owner group | Temporis Capital (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Blue Energy |
| Elexon lead party | Blackcraig Wind Farm Limited |
| BM unit | T_BLKWW-1 56 MW |
| Size | 88th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Blackcraig, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Blackcraig Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/blackcraig/ (Accessed: [date]).
Other Temporis Capital wind farms
- Tullymurdoch onshore, 14 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.