Millennium since 2019: every month and year
Elexon's metered record for Millennium's unit starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 1.2 TWh. Its busiest whole year was 2022, at a load factor of 32%. Its best day was 12 June 2019, when it generated 1,498 MWh, 62 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 119 GWh | 26% |
| 2025 | 131 GWh | 23% |
| 2024 | 156 GWh | 27% |
| 2023 | 144 GWh | 25% |
| 2022 | 183 GWh | 32% |
| 2021 | 133 GWh | 23% |
| 2020 | 164 GWh | 29% |
| 2019from 1 Feb | 152 GWh | 29% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_MILWW-1, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Millennium
Millennium is an onshore wind farm in Highland, Scotland, with 65 MW of registered generating capacity across one balancing mechanism unit. It is the 82nd largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Nadara. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Millennium as operational since July 2008, with 26 turbines of 2.5 MW, up to 125 m tall to the blade tip.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 65 MW |
| Turbines | 26 turbines of 2.5 MW |
| Height to blade tip | 125 m |
| Operational since | July 2008 |
| Location | Highland, Scotland |
| Owner group | Nadara (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Renewable Development |
| Elexon lead party | Millennium Wind Energy Ltd |
| BM unit | T_MILWW-1 65 MW |
| Size | 82nd largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Millennium, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Millennium Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/millennium/ (Accessed: [date]).
Other Nadara wind farms
- Farr onshore, 92 MW
- Kilbraur onshore, 69 MW
- Galawhistle onshore, 55 MW
- Causeymire onshore, 48 MW
- A'Chruach onshore, 43 MW
- Minsca onshore, 38 MW
- Auchrobert onshore, 36 MW
- Dalswinton onshore, 30 MW
- Assel Valley onshore, 26 MW
- Gordonstown onshore, 13 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.