Griffin since 2019: every month and year
Elexon's metered record for Griffin's units starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 2.3 TWh. Its busiest whole year was 2024, at a load factor of 18%. Its best day was 22 January 2026, when it generated 3,909 MWh, 163 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 274 GWh | 19% |
| 2025 | 309 GWh | 17% |
| 2024 | 322 GWh | 18% |
| 2023 | 275 GWh | 15% |
| 2022 | 297 GWh | 16% |
| 2021 | 244 GWh | 14% |
| 2020 | 277 GWh | 15% |
| 2019from 1 Feb | 283 GWh | 17% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its 2 units (T_GRIFW-1, T_GRIFW-2), fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Griffin
Griffin is an onshore wind farm in Tayside, Scotland, with 206 MW of registered generating capacity across 2 balancing mechanism units. It is the 40th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by SSE. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Griffin as operational since February 2012. SSE gives it 68 turbines of 2.3 MW.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 206 MW |
| Turbines | 68 turbines of 2.3 MW (SSE) |
| Operational since | February 2012 |
| Location | Tayside, Scotland |
| Owner group | SSE (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Greenpower (Griffin) |
| Elexon lead party | Griffin Wind Farm Ltd |
| BM units | T_GRIFW-1 102 MW, T_GRIFW-2 104 MW |
| Size | 40th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Griffin, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Griffin Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/griffin/ (Accessed: [date]).
Other SSE wind farms
- Dogger Bank A offshore, 1,200 MW
- Dogger Bank B offshore, 1,199 MW
- Seagreen offshore, 1,075 MW
- Beatrice offshore, 588 MW
- Clyde onshore, 550 MW
- Greater Gabbard offshore, 539 MW
- Viking onshore, 488 MW
- Stronelairg onshore, 228 MW
- Hadyard Hill onshore, 117 MW
- Bhlaraidh onshore, 108 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.