Galloper since 2019: every month and year
Elexon's metered record for Galloper's units starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 11.3 TWh. Its busiest whole year was 2020, at a load factor of 51%. Its best day was 22 March 2023, when it generated 8,249 MWh, 344 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 1.1 TWh | 45% |
| 2025 | 1.5 TWh | 47% |
| 2024 | 1.5 TWh | 48% |
| 2023 | 1.6 TWh | 51% |
| 2022 | 1.4 TWh | 45% |
| 2021 | 1.4 TWh | 46% |
| 2020 | 1.6 TWh | 51% |
| 2019from 1 Feb | 1.3 TWh | 45% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its 4 units (T_GANW-11, T_GANW-22, T_GANW-13, T_GANW-24), fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Galloper
Galloper is an offshore wind farm off the coast of England, with 353 MW of generating capacity across 4 balancing mechanism units: Elexon registers them at 650 MW in all, but Galloper Wind Farm gives it 353 MW, and that is the capacity this page uses. It is the 26th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by RWE. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Galloper as operational since March 2018, with 56 turbines of 6.3 MW.
| Type | Offshore wind farm |
|---|---|
| Capacity | 353 MW (Galloper Wind Farm) |
| Registered capacity | 650 MW (Elexon) |
| Turbines | 56 turbines of 6.3 MW |
| Operational since | March 2018 |
| Location | Off the coast of England |
| Owner group | RWE (operator or majority owner; joint ventures simplified) |
| Operator in REPD | RWE Npower Renewables |
| Elexon lead party | Galloper Offshore WindFarm Ltd |
| BM units | T_GANW-11 88 MW, T_GANW-22 386 MW, T_GANW-13 88 MW, T_GANW-24 88 MW |
| Size | 26th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Galloper, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Galloper Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/galloper/ (Accessed: [date]).
Other RWE wind farms
- Sofia offshore, 1,400 MW
- Triton Knoll offshore, 824 MW
- London Array offshore, 630 MW
- Gwynt y Môr offshore, 592 MW
- Rampion offshore, 400 MW
- Humber Gateway offshore, 219 MW
- Robin Rigg offshore, 174 MW
- Enoch Hill onshore, 70 MW
- Camster onshore, 50 MW
- Camster II onshore, 36 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.