Loading the live figure from Elexon…
Output over the last 7 days
Douglas West since 2021: every month and year
Elexon's metered record for Douglas West's unit starts on 4 May 2021, and runs to 24 October 2026. In that time it has generated 473 GWh. Its busiest whole year was 2022, at a load factor of 30%. Its best day was 28 June 2022, when it generated 982 MWh, 41 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 62.8 GWh | 20% |
| 2025 | 80.5 GWh | 20% |
| 2024 | 80.4 GWh | 20% |
| 2023 | 88.2 GWh | 22% |
| 2022 | 117 GWh | 30% |
| 2021from 4 May | 44.3 GWh | 17% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_DOUGW-1, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Douglas West
Douglas West is an onshore wind farm in Lanarkshire, Scotland, with 45 MW of registered generating capacity across one balancing mechanism unit. It is the 108th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Greencoat UK Wind. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.
The government's Renewable Energy Planning Database lists Douglas West as operational since January 2023, with 13 turbines of 4.2 MW, up to 150 m tall to the blade tip.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 45 MW |
| Turbines | 13 turbines of 4.2 MW |
| Height to blade tip | 150 m |
| Operational since | January 2023 |
| Location | Lanarkshire, Scotland |
| Owner group | Greencoat UK Wind (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Greencoat |
| Elexon lead party | Erova Energy Limited |
| BM unit | T_DOUGW-1 45 MW |
| Size | 108th largest of 163 |
Download and cite
Douglas West daily output (CSV)
Every finished UK day GridMonkey has recorded for Douglas West, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Douglas West Wind Farm: Live Output and History Since 2021. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/douglas-west/ (Accessed: [date]).
Other Greencoat UK Wind wind farms
- South Kyle onshore, 240 MW
- Braes of Doune onshore, 74 MW
- Corriegarth onshore, 69 MW
- Kype Muir Extension onshore, 67 MW
- Glen Kyllachy onshore, 52 MW
- Dalquhandy onshore, 43 MW
- Windy Rig onshore, 43 MW
- Tom nan Clach onshore, 40 MW
- Twenty Shilling onshore, 38 MW
- Andershaw onshore, 35 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since May 2021 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.