Burbo Bank wind farm

Burbo Bank is an offshore wind farm off the coast of England with 90 MW of registered capacity. In 2025 it generated 245 GWh, a load factor of 31%. What it is generating right now and over the last week, live from Elexon, the GB electricity market's data service, and every month since February 2019.

Generating now
– MW

Loading the live figure from Elexon…

Output over the last 7 days

Loading the last 7 days…

Burbo Bank since 2019: every month and year

Elexon's metered record for Burbo Bank's unit starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 1.9 TWh. Its busiest whole year was 2020, at a load factor of 37%. Its best day was 1 February 2023, when it generated 2,102 MWh, 88 MW on average.

Its average output each month, in MW. The dashed line is its capacity today, 90 MW. Hover over or tap a bar for the month’s figures.
Burbo Bank's metered output by year
YearGeneratedLoad factor
2026to 24 Oct216 GWh34%
2025245 GWh31%
2024244 GWh31%
2023217 GWh28%
2022233 GWh30%
2021217 GWh28%
2020293 GWh37%
2019from 1 Feb219 GWh30%

Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, E_BURBO, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.

About Burbo Bank

Burbo Bank is an offshore wind farm off the coast of England, with 90 MW of registered generating capacity across one balancing mechanism unit. It is the 62nd largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Ørsted. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.

The government's Renewable Energy Planning Database lists Burbo Bank as operational since October 2007, with 25 turbines of 3.6 MW.

Burbo Bank
Where Burbo Bank is, from its REPD location. Map outline: Natural Earth.
TypeOffshore wind farm
Registered capacity90 MW
Turbines25 turbines of 3.6 MW
Operational sinceOctober 2007
LocationOff the coast of England
Connects inNorth Wales and Merseyside
Owner groupØrsted (operator or majority owner; joint ventures simplified)
Operator in REPDØrsted
Elexon lead partyOrsted Burbo (UK) Limited
BM unit E_BURBO 90 MW
Size62nd largest of 163

Download and cite

Burbo Bank daily output (CSV)

Every finished UK day GridMonkey has recorded for Burbo Bank, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.

Cite this page (Harvard)

Energycount (2026) Burbo Bank Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/burbo-bank/ (Accessed: [date]).

Other Ørsted wind farms

Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.

Every wind farm in Britain, live

GridMonkey shows the whole GB generation mix as one big pie, and every wind farm's output right now. Free, no sign-up.