Crystal Rig II wind farm

Crystal Rig II is an onshore wind farm in Borders, Scotland with 151 MW of registered capacity. In 2025 it generated 285 GWh, a load factor of 22%. What it is generating right now and over the last week, live from Elexon, the GB electricity market's data service, and every month since February 2019.

Generating now
– MW

Loading the live figure from Elexon…

Output over the last 7 days

Loading the last 7 days…

Crystal Rig II since 2019: every month and year

Elexon's metered record for Crystal Rig II's unit starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 2.5 TWh. Its busiest whole year was 2020, at a load factor of 29%. Its best day was 29 January 2023, when it generated 3,187 MWh, 133 MW on average.

Its average output each month, in MW. The dashed line is its capacity today, 151 MW. Hover over or tap a bar for the month’s figures.
Crystal Rig II's metered output by year
YearGeneratedLoad factor
2026to 24 Oct273 GWh25%
2025285 GWh22%
2024316 GWh24%
2023287 GWh22%
2022348 GWh26%
2021307 GWh23%
2020380 GWh29%
2019from 1 Feb300 GWh25%

Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_CRYRW-2, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.

About Crystal Rig II

Crystal Rig II is an onshore wind farm in Borders, Scotland, with 151 MW of registered generating capacity across one balancing mechanism unit. It is the 46th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Fred. Olsen Renewables. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since 17 October 2026 for the chart.

The government's Renewable Energy Planning Database lists Crystal Rig II as operational since October 2010, with 60 turbines of 2.3 MW.

Crystal Rig II
Where Crystal Rig II is, from its REPD location. Map outline: Natural Earth.
TypeOnshore wind farm
Registered capacity151 MW
Turbines60 turbines of 2.3 MW
Operational sinceOctober 2010
LocationBorders, Scotland
Owner groupFred. Olsen Renewables (operator or majority owner; joint ventures simplified)
Operator in REPDFred Olsen Renewables
Elexon lead partyEneco Energy Trade
BM unit T_CRYRW-2 151 MW
Size46th largest of 163

Download and cite

Crystal Rig II daily output (CSV)

Every finished UK day GridMonkey has recorded for Crystal Rig II, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.

Cite this page (Harvard)

Energycount (2026) Crystal Rig II Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/crystal-rig-ii/ (Accessed: [date]).

Other Fred. Olsen Renewables wind farms

Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.

Every wind farm in Britain, live

GridMonkey shows the whole GB generation mix as one big pie, and every wind farm's output right now. Free, no sign-up.