Output over the last 7 days
Mid Hill since 2019: every month and year
Elexon's metered record for Mid Hill's unit starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has generated 1.0 TWh. Its busiest whole year was 2022, at a load factor of 29%. Its best day was 26 September 2020, when it generated 1,738 MWh, 72 MW on average.
| Year | Generated | Load factor |
|---|---|---|
| 2026to 24 Oct | 15.1 GWh | 3% |
| 2025 | 73.1 GWh | 11% |
| 2024 | 72.5 GWh | 11% |
| 2023 | 145 GWh | 22% |
| 2022 | 195 GWh | 29% |
| 2021 | 135 GWh | 20% |
| 2020 | 194 GWh | 29% |
| 2019from 1 Feb | 172 GWh | 28% |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, 2__PSTAT002, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Mid Hill
Mid Hill is an onshore wind farm in Grampian, Scotland, with 76 MW of registered generating capacity across one balancing mechanism unit. It is the 68th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Fred. Olsen Renewables. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since it was added to the list in October 2026 for the chart.
The government's Renewable Energy Planning Database lists Mid Hill as operational since December 2013, with 33 turbines of 2.3 MW.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 76 MW |
| Turbines | 33 turbines of 2.3 MW |
| Operational since | December 2013 |
| Location | Grampian, Scotland |
| Grid region | North Scotland |
| Owner group | Fred. Olsen Renewables (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Fred Olsen Renewables |
| Elexon lead party | Statkraft Markets Gmbh |
| BM unit | 2__PSTAT002 76 MW |
| Size | 68th largest of 163 |
Download and cite
Every finished UK day GridMonkey has recorded for Mid Hill, up to the last 12 months: the energy it generated, its average output and its load factor. The output is what the farm told the grid it would generate (its physical notification), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Mid Hill Wind Farm: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/wind-farms/mid-hill/ (Accessed: [date]).
Other Fred. Olsen Renewables wind farms
- Crystal Rig II onshore, 151 MW
- Paul's Hill onshore, 70 MW
- Brockloch Rig 2 onshore, 62 MW
- Rothes onshore, 55 MW
- Crystal Rig IV onshore, 48 MW
- Rothes II onshore, 42 MW
- Crystal Rig III onshore, 14 MW
More wind farms in North Scotland
- Braes of Doune onshore, 74 MW
- Berry Burn onshore, 63 MW
- Moy onshore, 60 MW
- Baillie onshore, 53 MW
- Beinn an Tuirc III onshore, 52 MW
- Camster onshore, 50 MW
- Kincardine offshore, 50 MW
- Causeymire onshore, 48 MW
- Hill of Towie onshore, 48 MW
- Beinn an Tuirc 2 onshore, 44 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2019 is its metered output (B1610). Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.