Loading the live figure from Elexon…
Output over the last 7 days
About Rothes
Rothes is an onshore wind farm in Grampian, Scotland, with 55 MW of registered generating capacity across one balancing mechanism unit. It is the 89th largest of the 163 wind farms in GridMonkey's list of Britain's wind farms that report to Elexon, and is operated or mostly owned by Fred. Olsen Renewables. Every half hour it tells the grid how much it will generate (its physical notification). That is the live figure above, and GridMonkey has recorded it every half hour since it was added to the list in October 2026 for the chart.
The government's Renewable Energy Planning Database lists Rothes as operational since November 2004, with 22 turbines of 2.3 MW.
| Type | Onshore wind farm |
|---|---|
| Registered capacity | 55 MW |
| Turbines | 22 turbines of 2.3 MW |
| Operational since | November 2004 |
| Location | Grampian, Scotland |
| Grid region | North Scotland |
| Owner group | Fred. Olsen Renewables (operator or majority owner; joint ventures simplified) |
| Operator in REPD | Natural Power Consultants |
| Elexon lead party | Eneco Energy Trade |
| BM unit | 2__PENEC001 55 MW |
| Size | 89th largest of 163 |
Other Fred. Olsen Renewables wind farms
- Crystal Rig II onshore, 151 MW
- Mid Hill onshore, 76 MW
- Paul's Hill onshore, 70 MW
- Brockloch Rig 2 onshore, 62 MW
- Crystal Rig IV onshore, 48 MW
- Rothes II onshore, 42 MW
- Crystal Rig III onshore, 14 MW
More wind farms in North Scotland
- Braes of Doune onshore, 74 MW
- Berry Burn onshore, 63 MW
- Moy onshore, 60 MW
- Baillie onshore, 53 MW
- Beinn an Tuirc III onshore, 52 MW
- Camster onshore, 50 MW
- Kincardine offshore, 50 MW
- Causeymire onshore, 48 MW
- Hill of Towie onshore, 48 MW
- Beinn an Tuirc 2 onshore, 44 MW
All 163 wind farms, live → Every wind farm on a live map → Wind farm league table → Other power stations, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Farm names and owner groups are GridMonkey's reading of Elexon's register; a farm's output here is its physical notification, not metered generation. Turbines, location, status and operator: Renewable Energy Planning Database (DESNZ, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.