Elexon's metered record for Sundon's unit starts on 14 July 2024, and runs to 24 October 2026. In that time it has supplied 68.1 GWh and taken 80.7 GWh while charging, giving back 84% of what it took. Its best day was 3 February 2026, when it supplied 235 MWh, 10 MW on average.
| Year | Supplied | Took while charging | Load factor | Days supplying |
|---|---|---|---|---|
| 2026to 24 Oct | 35.5 GWh | 41.8 GWh | 10% | 297 |
| 2025 | 28.8 GWh | 34.2 GWh | 7% | 343 |
| 2024from 14 Jul | 3.8 GWh | 4.7 GWh | 2% | 59 |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, T_SUNDB-1, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for; a day counts as one it supplied power on if it supplied at least 2% of its capacity (or 1 MW) in any half hour. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Sundon
Sundon is a battery storage site at Chalton, near Luton, in Bedfordshire. It began operating in December 2025.
Its 50 MW of registered generating capacity is spread across one balancing mechanism unit. Every half hour each unit tells the grid how much it will generate (its physical notification): that is the live figure above, and GridMonkey records it every half hour for the chart.
Battery stations charge when power is cheap and plentiful and discharge at the peaks, in seconds. Their output swings between charging and discharging through the day.
| Type | Battery storage |
|---|---|
| Registered capacity | 50 MW |
| Operational since | December 2025 (REPD) |
| Area | Bedfordshire |
| Location | At Chalton, near Luton, in Bedfordshire 51.931° N, 0.499° W |
| Operator in REPD | Pivot Power (EDF) (REPD) |
| Elexon lead party | Pivoted Power LLP |
| BM unit | T_SUNDB-1 50 MW |
| Size | 52nd largest of the 79 battery storage sites on GridMonkey's list |
Download and cite
Every finished UK day GridMonkey has recorded for Sundon, up to the last 12 months: the energy it generated, its average output, load factor and peak, and the hours it ran, and what it took from the grid while it charged. The output is what its units told the grid they would generate (their physical notifications), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Sundon Battery Storage: Live Output and History Since 2024. Available at: https://energycount.co.uk/tools/grid-mix/power-stations/sundon/ (Accessed: [date]).
Other battery storage sites
- Coalburn 518 MW, South Lanarkshire
- Hams Hall 400 MW, Warwickshire
- Monk Fryston 320 MW, North Yorkshire
- Kilmarnock South 313 MW, East Ayrshire
- Thurrock 300 MW, Essex
- Sheaf 249 MW, Kent
- Uskmouth 232 MW, Newport
- Blackhillock 208 MW, Moray
- Thornton 200 MW, East Riding of Yorkshire
- Ferrybridge 152 MW, West Yorkshire
- Wilton battery 150 MW, Teesside
- Iron Acton 121 MW, South Gloucestershire
All 158 power stations, live → Power station league table → Power station outages now → Every wind farm, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Station names come from GridMonkey's own table, matched to the units in Elexon's register; a station's live output and last 7 days here are its physical notifications, not metered generation, and its record since July 2024 is its metered output (B1610). Operator, operational date, area and location: Renewable Energy Planning Database (REPD) (Department for Energy Security and Net Zero, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.