Checking Elexon for Richborough Energy Park's output this half hour…
Loading the live figure from Elexon…
Output over the last 7 days
Richborough Energy Park since 2023: every month and year
Elexon's metered record for Richborough Energy Park's units starts on 25 July 2023, and runs to 24 October 2026. In that time it has supplied 112 GWh and taken 131 GWh while charging, giving back 85% of what it took. Its busiest whole year was 2025, at a load factor of 5%. Its best day was 30 March 2026, when it supplied 266 MWh, 11 MW on average.
| Year | Supplied | Took while charging | Load factor | Days supplying |
|---|---|---|---|---|
| 2026to 24 Oct | 30.3 GWh | 35.3 GWh | 4% | 297 |
| 2025 | 41.8 GWh | 48.6 GWh | 5% | 365 |
| 2024 | 36 GWh | 42.4 GWh | 4% | 366 |
| 2023from 25 Jul | 3.5 GWh | 4.5 GWh | 0.8% | 64 |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its 2 units (T_RICHB-1, T_RICHB-2), fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for; a day counts as one it supplied power on if it supplied at least 2% of its capacity (or 1 MW) in any half hour. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Richborough Energy Park
Richborough Energy Park is a battery storage site at Richborough, near Sandwich, in Kent. It began operating in December 2023. It shares the old Richborough power station site with Sheaf, a larger battery, and has been owned by Sosteneo's Energy Transition Fund since 2023.
Its 100 MW of registered generating capacity is spread across 2 balancing mechanism units. Every half hour each unit tells the grid how much it will generate (its physical notification): that is the live figure above, and GridMonkey has recorded it every half hour since it was added to the list in October 2026, for the chart.
Battery stations charge when power is cheap and plentiful and discharge at the peaks, in seconds. Their output swings between charging and discharging through the day.
| Type | Battery storage |
|---|---|
| Registered capacity | 100 MW |
| Operational since | December 2023 (REPD) |
| Area | Kent |
| Location | At Richborough, near Sandwich, in Kent 51.312° N, 1.343° E |
| Elexon lead party | Limejump Energy Limited |
| BM units | T_RICHB-1 50 MW, T_RICHB-2 50 MW |
| Size | 18th largest of the 79 battery storage sites on GridMonkey's list |
Download and cite
Richborough Energy Park daily output (CSV)
Every finished UK day GridMonkey has recorded for Richborough Energy Park, up to the last 12 months: the energy it generated, its average output, load factor and peak, and the hours it ran, and what it took from the grid while it charged. The output is what its units told the grid they would generate (their physical notifications), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Richborough Energy Park Battery Storage: Live Output and History Since 2023. Available at: https://energycount.co.uk/tools/grid-mix/power-stations/richborough-energy-park/ (Accessed: [date]).
Other battery storage sites
- Coalburn 518 MW, South Lanarkshire
- Hams Hall 400 MW, Warwickshire
- Monk Fryston 320 MW, North Yorkshire
- Kilmarnock South 313 MW, East Ayrshire
- Thurrock 300 MW, Essex
- Sheaf 249 MW, Kent
- Uskmouth 232 MW, Newport
- Blackhillock 208 MW, Moray
- Thornton 200 MW, East Riding of Yorkshire
- Ferrybridge 152 MW, West Yorkshire
- Wilton battery 150 MW, Teesside
- Iron Acton 121 MW, South Gloucestershire
All 158 power stations, live → Power station league table → Power station outages now → Every wind farm, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Station names come from GridMonkey's own table, matched to the units in Elexon's register; a station's live output and last 7 days here are its physical notifications, not metered generation, and its record since July 2023 is its metered output (B1610). Operational date, area and location: Renewable Energy Planning Database (REPD) (Department for Energy Security and Net Zero, July 2026). Contains public sector information licensed under the Open Government Licence v3.0.