Cruachan is a 453 MW pumped storage hydro station on Loch Awe in Argyll and Bute, operated or mostly owned by Drax. In 2025 it supplied 367 GWh and took 424 GWh while pumping. Is it running right now? Its live output from Elexon, the GB electricity market's data service, every half hour of the last week, and every month since February 2019.
Checking Elexon for Cruachan's output this half hour…
Generating now
– MW
Loading the live figure from Elexon…
Output over the last 7 days
Supplying the grid (above the line)Pumping: taking power (below the line)
Elexon's metered record for Cruachan's units starts on 1 February 2019, the start of its archive, and runs to 24 October 2026. In that time it has supplied 2.6 TWh and taken 2.9 TWh while pumping, giving back 87% of what it took. Its busiest whole year was 2024, at a load factor of 12%. Its best day was 5 July 2024, when it supplied 5,228 MWh, 218 MW on average.
200 MW100 MW200 MW taken
20192020202120222023202420252026
Its average output each month, in MW; below the line, what it took from the grid while pumping. Its capacity today is 453 MW, well above any month’s average, so the chart is scaled to its months. Hover over or tap a bar for the month’s figures.
Cruachan's metered output by year
Year
Supplied
Took while pumping
Load factor
Days supplying
2026to 24 Oct
259 GWh
287 GWh
8%
259
2025
367 GWh
424 GWh
9%
336
2024
473 GWh
572 GWh
12%
353
2023
421 GWh
507 GWh
11%
350
2022
319 GWh
370 GWh
8%
342
2021
234 GWh
291 GWh
6%
338
2020
266 GWh
272 GWh
7%
340
2019from 1 Feb
217 GWh
218 GWh
6%
304
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation
unit, as settled) for its 4 units (T_CRUA-1, T_CRUA-2, T_CRUA-3, T_CRUA-4), fetched on 2026-11-16. Load factor is against its capacity today, over
the half hours Elexon has figures for; a day counts as one it supplied power on if it supplied at least 2% of its capacity (or 1 MW) in any half hour.
The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Cruachan
Cruachan is a pumped storage hydro station on Loch Awe in Argyll and Bute. It was commissioned in 1965. It pumps water uphill to its top reservoir when power is plentiful, and lets it back down through turbines when the grid needs it.
Its 453 MW of registered generating capacity is spread across 4 balancing mechanism units.
Every half hour each unit tells the grid how much it will generate (its physical notification): that is the live
figure above, and GridMonkey records it every half hour for the chart.
Pumped storage stations are giant water batteries: they pump water uphill when power is plentiful and generate when the grid needs it, within a minute or two.
Where Cruachan is. DUKES 5.11's grid reference is about 10 km out, so the map uses OpenStreetMap's position for the station. Map outline: Natural Earth.
Type
Pumped storage hydro
Registered capacity
453 MW
Commissioned
1965 (DUKES 5.11)
Area
Argyll and Bute
Location
On Loch Awe in Argyll and Bute 56.394° N, 5.114° W
Every finished UK day GridMonkey has recorded for Cruachan, up to the last 12 months: the energy it generated, its
average output, load factor and peak, and the hours it ran, and what it took from the grid while it pumped.
The output is what its units told the grid they would generate (their physical notifications), not metered
generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column
means.
Cite this page (Harvard)
Energycount (2026) Cruachan Pumped Storage Power Station: Live Output and History Since 2019. Available at: https://energycount.co.uk/tools/grid-mix/power-stations/cruachan/ (Accessed: [date]).