Checking Elexon for Croydon's output this half hour…
Loading the live figure from Elexon…
Output over the last 7 days
Croydon since 2022: every month and year
Elexon's metered record for Croydon's unit starts on 21 February 2022, and runs to 24 October 2026. In that time it has generated 39.1 GWh. Its busiest whole year was 2023, at a load factor of 2%. Its best day was 15 December 2022, when it generated 534 MWh, 22 MW on average.
| Year | Generated | Load factor | Days it ran |
|---|---|---|---|
| 2026to 24 Oct | 2.1 GWh | 0.6% | 22 |
| 2025 | 186 MWh | 0% | 3 |
| 2024 | 2.8 GWh | 0.6% | 46 |
| 2023 | 7.5 GWh | 2% | 68 |
| 2022from 21 Feb | 26.4 GWh | 7% | 162 |
Metered output from Elexon's Balancing Mechanism Reporting Service (B1610, actual generation output per generation unit, as settled) for its one unit, E_CROYD-2, fetched on 2026-11-16. Load factor is against its capacity today, over the half hours Elexon has figures for; a day counts as one it ran if it generated at least 2% of its capacity (or 1 MW) in any half hour. The live figure and the last 7 days above are its physical notifications, which GridMonkey records itself.
About Croydon
Croydon is an open-cycle gas turbine (OCGT) station in Croydon, south London. It was commissioned in 2005. It starts quickly to cover peaks in demand.
Its 50 MW of registered generating capacity is spread across one balancing mechanism unit. Every half hour each unit tells the grid how much it will generate (its physical notification): that is the live figure above, and GridMonkey has recorded it every half hour since it was added to the list in October 2026, for the chart.
Gas stations follow demand: they ramp up when the wind drops or the evening peak arrives, and back off when there is plenty of wind and sun. Most are combined-cycle (CCGT); a few open-cycle turbines (OCGT) start fast to cover peaks.
| Type | Open-cycle gas turbine (OCGT) station |
|---|---|
| Registered capacity | 50 MW |
| Commissioned | 2005 (DUKES 5.11) |
| Area | London |
| Location | In Croydon, south London 51.376° N, 0.116° W |
| Owner or operator | Rockland Capital |
| Elexon lead party | Whitetower Energy Limited |
| BM unit | E_CROYD-2 50 MW |
| Size | 41st largest of the 45 gas power stations on GridMonkey's list |
Download and cite
Every finished UK day GridMonkey has recorded for Croydon, up to the last 12 months: the energy it generated, its average output, load factor and peak, and the hours it ran. The output is what its units told the grid they would generate (their physical notifications), not metered generation. Free to reuse under CC BY 4.0 with credit to GridMonkey: what each column means.
Cite this page (Harvard)
Energycount (2026) Croydon Power Station: Live Output and History Since 2022. Available at: https://energycount.co.uk/tools/grid-mix/power-stations/croydon/ (Accessed: [date]).
Other gas power stations
- Pembroke 2,375 MW, Pembrokeshire
- Staythorpe 1,856 MW, Nottinghamshire
- Didcot B 1,490 MW, Oxfordshire
- Connah's Quay 1,412 MW, Flintshire
- West Burton B 1,410 MW, Nottinghamshire
- Grain 1,326 MW, Kent
- Immingham CHP 1,283 MW, Lincolnshire
- Seabank 1,236 MW, Bristol
- Saltend 1,226 MW, East Riding of Yorkshire
- Peterhead 1,200 MW, Aberdeenshire
- Spalding 950 MW, Lincolnshire
- Carrington 940 MW, Greater Manchester
All 158 power stations, live → Power station league table → Power station outages now → Every wind farm, live →
Contains BMRS data © Elexon Limited copyright and database right 2026 (licence). Station names, areas and owners or operators come from GridMonkey's own table, matched to the units in Elexon's register; a station's live output and last 7 days here are its physical notifications, not metered generation, and its record since February 2022 is its metered output (B1610). Year commissioned and location: Power stations in the United Kingdom (DUKES 5.11) (Department for Energy Security and Net Zero, May 2026). Contains public sector information licensed under the Open Government Licence v3.0.