About Moyle
Moyle runs about 64 km from Auchencrosh, near Ballantrae, South Ayrshire, to Ballycronan More, Islandmagee, County Antrim, Northern Ireland. It has been in service since 2002 (commissioned in 2001). Its limits differ by direction: Mutual Energy gives 450 MW from Scotland to Northern Ireland and 400 MW the other way.
Like all of Britain's interconnectors it carries direct current, and power can flow either way. Which way it flows is set by the electricity markets at each end: power generally flows towards whichever side's price is higher. The live figure above is Elexon's, every five minutes: positive when power is coming into Great Britain, negative when it is going out. The chart uses Elexon's half-hourly figures, which GridMonkey records every half hour.
| Connects | Great Britain and Northern Ireland |
|---|---|
| Capacity | 500 MW, either way |
| In Britain | Auchencrosh, near Ballantrae, South Ayrshire 55.069° N, 4.981° W |
| Other end | Ballycronan More, Islandmagee, County Antrim, Northern Ireland |
| Owners | Mutual Energy |
| In service since | 2002 (commissioned in 2001) |
| Length | About 64 km |
| Technology | HVDC, 250 kV |
| Elexon fuel type | INTIRL |
Britain's other interconnectors
- IFA France, 2,000 MW
- IFA2 France, 1,000 MW
- ElecLink France, 1,000 MW
- BritNed the Netherlands, 1,000 MW
- Nemo Link Belgium, 1,000 MW
- North Sea Link Norway, 1,400 MW
- Viking Link Denmark, 1,400 MW
- East West Ireland, 500 MW
- Greenlink Ireland, 500 MW