New build compliance: what you need at each stage

A new home collects a surprising number of reports on its way from sketch to completion certificate. Each one is due at a particular point, and most of the expensive problems come from getting to that point without it. Here is the whole sequence for a new dwelling in England, stage by stage: what's needed, when it's due, and what goes wrong if it's late.

— reviewed against the regs as they stand.

Quick answer: A new dwelling in England needs, in order: planning, which may ask for an energy statement, a nutrient neutrality assessment and the 110-litre water standard; before work starts, the design-stage SAP and BREL report with the Part O overheating assessment; during the build, photographs of the insulation and a water calculation before the sanitaryware is ordered; before completion, an air test on every dwelling and sound tests on attached ones; and within five days of completion, the as-built SAP, the completion BREL, the EPC and the Part G notice. The completion certificate waits for all of them.

The whole sequence on one page

StageWhat’s neededWhat goes wrong if it’s late
1. FeasibilityA quick check of the site’s catchment, water stress and local energy policyA planning requirement you didn’t price
2. Planning applicationEnergy statement where local policy asks; nutrient neutrality assessment in an affected catchmentApplication stalled or refused
3. Pre-commencement conditionsEvidence to discharge the energy, water and nutrient conditionsWork that starts is unauthorised
4. Building Regs applicationDesign-stage SAP, Part O overheating, U-values and junction detailsA specification that can’t pass
5. Before work startsDesign-stage BREL notified by the day before; Robust Details registration if you’re using it; a PEA if you’re selling off-planA notice breach, or no route out of sound testing
6. ConstructionPhotographic evidence of every insulation detail; Part G water calculation before the bathroom order; SAP re-run on any specification changePlots that can’t be signed off
7. Pre-completionAir test on every dwelling; sound tests on attached onesA failed test with the decorators in
8. Within 5 days of completionAs-built SAP, completion BREL with the photos, the EPC, the Part G notice, the home user guideNo completion certificate, so no sale

The rest of this page takes each stage in turn.

1. Feasibility: before anyone draws it properly

Three things about the site can each add a report and a cost. It’s much better to know them before the land price or the layout is fixed.

2. The planning application

Planning deals with local policy, not Building Regulations. Where local policy calls for it, you’ll need an energy statement showing how the scheme meets the council’s renewables or carbon target. In an affected catchment you’ll need a nutrient neutrality assessment, prepared to Natural England’s methodology. In London, the London Plan adds its own carbon target on top of Part L.

The energy statement is modelled in SAP, so doing it properly now gives you a head start on the design-stage calculation later.

3. Discharging the pre-commencement conditions

Energy and water requirements are often attached to the permission as conditions, and some of them are pre-commencement: they must be discharged before any work starts. Read the decision notice carefully. “Prior to commencement” means exactly that, and work begun without discharging it is unauthorised. Typical ones are a detailed energy statement, confirmation of the 110-litre water standard, and, in a nutrient catchment, proof that the mitigation credits are secured.

4. The Building Regulations application

This is where most of the calculation work happens, and the cheapest point to change the answer.

5. Before work starts

The regulations fix one deadline here. The target rates, the as-designed rates and the list of specifications the calculation depends on must be notified to Building Control by the day before work begins, on the design-stage BREL report.

Two other things belong here:

6. During construction

This is the stage people think needs nothing from the assessor, and it’s where most completion problems start.

7. Pre-completion testing

Book both early. Each test needs the building in a particular state, and a failed test has to be remediated and retested before completion.

8. Completion: the five-day window

Within five days of completion:

Building Control can’t issue the completion certificate without these, and without the certificate the sale can’t complete. Five days is the legal backstop, not a target. Most of what goes in the completion pack can be prepared as the build progresses, so the window is used for signatures rather than chasing.

Commercial buildings follow the same shape

A building other than a dwelling runs on the same pattern with different paperwork. SBEM replaces SAP, and the BRUKL report replaces the BREL: one before work starts, one within five days of completion. The non-domestic EPC is lodged from the as-built model, and the air tightness limit is the same. Planning can still ask for an energy statement or BREEAM, depending on the council.

Conversions and extensions are shorter

The bottom line

Nearly every late-stage compliance problem is an earlier stage that got skipped. The fixes that are free on a drawing cost scaffolding and plaster once the house is up. If you tell us where your project has got to, we’ll tell you what it still needs. The New Build Compliance Pack covers the SAP, EPC, water, air and sound testing as one job with one set of assumptions.

Common questions

What reports does a new build house need?

For Building Regulations in England: a design-stage SAP calculation and BREL report before work starts, a Part O overheating assessment, a Part G water efficiency calculation, an air tightness test, sound tests if the home is attached to another, photographic evidence of the insulation, and at completion the as-built SAP, the completion BREL report and the EPC. Planning may add an energy statement, a nutrient neutrality assessment and a tighter 110-litre water condition, depending on the site and the local plan.

When should I get the SAP calculation done?

At design stage, before the Building Regulations application if you can, and in any case before work starts, because the design-stage figures and specification have to be notified to Building Control by the day before work begins. Earlier is cheaper: a design that fails SAP can be fixed on paper by changing the specification, but once the frame is up the choices get expensive.

What has to be done within five days of completion?

The as-built SAP results and any changes to the specification go to Building Control on the completion-stage BREL report, with the photographic evidence. The EPC is lodged and given to the owner. The Part G water efficiency notice goes to Building Control under Regulation 37. The completion certificate depends on these, so in practice they are the last things on the programme and the ones most often late.

Do I need an energy statement for planning?

Only if your local planning authority's policies ask for one. Many do, often as a percentage reduction in energy demand or carbon from renewables, and some now set energy use intensity targets that need PHPP modelling. The requirement is usually a planning condition, sometimes pre-commencement, so it needs discharging before work starts.

Is the order different for a conversion or an extension?

Yes. A conversion into a dwelling still needs SAP, Part G water and an EPC, but not the target rates of a new build, the photographs or Part O. An extension usually needs no SAP at all, provided its glazing stays within the 25% rule and the elements meet the limiting U-values. The conversion and extension guides cover those routes.