Greater Cambridge's water objections are gone: what it means for new homes

Since 2022 the Environment Agency has objected to more than 9,000 homes in Greater Cambridge because there was not enough water to supply them. A government progress report published on 20 November says those objections have been withdrawn. Water efficiency still matters on Cambridge sites.

WaterMonkey — free in your browser

Turn a fittings schedule into litres per person per day

Enter the WCs, taps, bath, shower and appliances and WaterMonkey applies the Approved Document G Table 1 use factors, the normalisation and the external allowance — so you can see straight away whether the scheme clears 125 or 110.

Free to calculate. Building Control-ready PDF from £25 +VAT, covering every identical plot on the site.

Quick answer: On 20 November 2026 the government published Addressing water scarcity and wastewater capacity in Greater Cambridge: progress report. It says the Environment Agency has withdrawn the objections it had raised since 2022 to over 9,000 homes and 500,000 m² of commercial space on water supply grounds. As of November 2026, the report says, no planned development in Greater Cambridge is stalled in the planning system because of water supply. The proposed water credits scheme is not needed for now. None of this changes Part G, and it does not remove any water efficiency policy or planning condition that applies to your site.

What has happened

Greater Cambridge has been the clearest example in England of water supply holding up housing. The area depends heavily on groundwater from the chalk aquifer, and taking more water out risks harming chalk streams. From 2022 the Environment Agency (EA) objected to planning applications because it could not be confident there was enough sustainable water to supply them.

The new progress report, with a foreword from housing minister Matthew Pennycook and water minister Emma Hardy, sets out why that has changed. Two things gave the EA the assurance it needed:

With both in place, the report says the EA has withdrawn its objections. Planning Geek’s summary of the report makes a fair point: this removes a barrier, but it does not grant planning permission. Each application still has to meet its own policies and conditions.

The catch: it depends on delivery

The withdrawal is not unconditional. The report says growth in the emerging Greater Cambridge Local Plan can be accommodated within Cambridge Water’s plan subject to the water companies delivering their commitments on the agreed timelines. The main new supply is still years away:

Until those schemes arrive, the area’s water balance relies on using less water. That is why water efficiency on new homes is not going away in Cambridge.

Why water credits are off the table for now

In 2024 the government said it would pilot a water credits scheme. Developers would pay into a fund that saves water elsewhere, to offset the demand from their new homes. It worked in a similar way to nutrient credits.

The report says that is not currently needed, because the government is paying for the savings directly through the Water Efficiency Programme. That programme is expected to save up to 0.89 million litres a day, which the report says is equivalent to 3,180 new homes. So far it has included:

Cambridge Water also plans more than 14,500 further smart meters by 2030. The report does leave the door open: offsetting could come back if new risks to supply appear.

For developers, this means no new per-home water charge in Greater Cambridge for now. Offsetting is the job of the water company and the government, not something added to your viability appraisal.

What it does not change

Part G has not changed. The national minimum is still 125 litres per person per day, with the optional requirement of 110 l/p/d where a local plan policy or planning condition applies it. Defra’s proposal to tighten these to 105 and 100 l/p/d is still waiting for a government response. As we reported in our piece on Ofwat’s flow limiter decision, that change now looks at risk. For background on the proposal, see Part G heading for 105 litres.

Local water policies still apply. Cambridgeshire is one of the areas where the 110 l/p/d optional requirement is regularly applied through planning. The August 2026 NPPF still allows councils to require it, and in exceptional cases something tighter in areas of serious water stress. The progress report itself refers to tighter water efficiency standards for growth in the area, but it does not set a new figure. Check the current and emerging local plan policy, and the conditions on your decision notice, before you assume which target applies.

Lower water use is still expected. The report points to the Eddington development in north-west Cambridge, which was designed for around 80 litres per person per day using a dual-pipe system for recycled water. That system is installed but not yet working. The figure is not a standard, but it shows where expectations for large Cambridge sites are heading.

What to do now

WaterMonkey turns a fittings schedule into a litres per person per day figure using the Approved Document G method, so you can check a Cambridge scheme against 110 l/p/d before you commit to a specification. If you would like us to do the calculation for you, get in touch.

Got a project this affects?

WaterMonkey is free in your browser, so you can see where your own scheme lands before anyone else asks. Want it done for you instead? Send the drawings over.