The levy surge has landed at Gateway 2 — and BSR is pausing the weak applications

The Building Safety Regulator's data for August to October 2026, published on 6 November, confirms the rush to beat the 1 October Building Safety Levy: 64 new-build applications in September, then just 6 in October. The late arrivals are getting extra scrutiny, and 18 of them have been paused as poor quality.

Quick answer: The Building Safety Regulator’s latest transparency data, covering August to October 2026 (figures as of 1 November) and published on 6 November, shows new-build Gateway 2 applications rising from 17 in July to 34 in August and 64 in September, then falling to 6 in October, after the Building Safety Levy started on 1 October. Applications received from 21 September onwards are going through enhanced validation: of 41, 18 have been paused as poor quality and 8 are recommended for rejection. Meanwhile, decisions are getting faster. The median new-build approval time is now 20 weeks, with a 95% approval rate.

The surge, then the dip

In September we reported that BSR expected a rush of Gateway 2 applications before the Building Safety Levy took effect. The new building control approval application data for August to October 2026 shows how big that rush was.

New-build higher-risk applications (including conversions) received each month were:

Month (2026)New-build applications received
July17
August34
September64
October6

BSR received 96 new-build applications in the 12 weeks to 1 November. Three were invalidated and one was withdrawn. BSR describes the October figure as follows: “We believe this is a dip following the surge.” That fits the levy rules, which apply to building control approval applications submitted on or after 1 October 2026. Developers who could submit early did so.

Late arrivals get enhanced validation

The most useful part of this dataset for anyone with a scheme in the queue is how BSR is handling the late applications:

In plain terms, a September application rushed together to beat the levy is not guaranteed to go through. As our earlier article explained, a pre-October application that is rejected and then resubmitted after 1 October is liable for the levy. Where an application has been paused or recommended for rejection, the applicant should confirm with BSR which date it will be treated as having been made before deciding how to respond.

Performance: faster decisions, high approval rates

For the rolling 12 weeks to 1 November:

There are now 242 live major change requests. The median closure time for new-build projects is still 7 weeks, one week over the statutory target. That is the figure to plan around when a design changes after Gateway 2 approval.

Two things that haven’t changed

Gateway 3 is still empty for new build. BSR says that “No new build projects that have passed through gateway 2 have reached gateway 3.” The first completions-stage test of the new regime is still to come.

Inspections are still finding deviations. BSR repeats that its new-build inspection regime “has highlighted a small amount of building work that deviates” from approved designs. It says it will “take a rigorous approach to ensure that safety is not compromised”.

What this means for your scheme

If your higher-risk scheme went in during the September rush, check where it stands now. A paused application is a chance to fix the submission while it is still treated as a pre-levy application. A rejection may mean the resubmission is liable for the levy. Either way, BSR is clearly testing the quality of what was submitted, not just whether it arrived on time.

For schemes not yet submitted, the levy is now part of the cost. The deadline that remains is the Future Homes Standard transitional cut-off. A higher-risk building keeps Part L 2021 only if a valid Gateway 2 application is made before 24 September 2027 and work starts in time (our transitional explainer has the detail). The September experience suggests that a late, rushed application is the one most likely to be paused.

The energy evidence is part of that quality test. The SAP calculation, fabric U-values, junction Ψ-values and Part F ventilation strategy all need to match the drawings and specification in the same submission.

Getting the Part L evidence right first time

If you have a higher-risk scheme heading for Gateway 2, whether it is a paused September application or one aiming for the 2027 transitional deadline, we can prepare or check the SAP and Part L evidence so that it matches the rest of the submission.

Talk to us about SAP calculations for new builds or get in touch.

Sources: Building Safety Regulator building control approval application data August to October 2026 (GOV.UK, published 6 November 2026) · Building control approval application data August to October 2026 (PDF) · Building Safety Regulator building control approval application data June to August 2026 (GOV.UK)